What to know about the $10 billion data center proposed north of Lacy Lakeview
The project needs land, water and Waco's cooperation, and neighbors have organized against it.

A developer called Infrakey wants to build a roughly $10 billion data center campus on about 520 acres of farmland north of Lacy Lakeview, near Elm Mott. It would be the largest industrial project in McLennan County's history.
The partnership. Lacy Lakeview approved a non-binding agreement in December 2025 to annex the site and provide utilities. Because the land sits in Waco's extraterritorial jurisdiction, Infrakey asked Waco in May 2026 to release it so Lacy Lakeview could annex it.
The water question. Published estimates put the campus's need at about 2 million gallons a day at full buildout. Lacy Lakeview has pitched reclaimed wastewater, but that plan depends on infrastructure Waco controls.
The pushback. Rural neighbors launched a petition with more than 1,500 signatures, raising concerns about water, power and the area's farm character.
254 Texas Insider will keep tracking the project as Waco, Lacy Lakeview and the developer make their next moves.