Bell County locks in $14.05 million construction price for Justice Center Annex
The guaranteed maximum price brings the full project budget to about $16 million.

Bell County commissioners on Monday approved a guaranteed maximum price of $14.05 million from Cloud Construction for the Justice Center Annex.
With design and other costs included, the county puts the total project budget at roughly $16 million. A guaranteed maximum price caps what the county pays the builder for the agreed scope of work.
The vote came during the same meeting in which the court accepted $16.75 million in road grants and certified the November election.